Joylive has achieved it with practical actions: only 10 days from the start of construction to the successful completion, and only 12 days from the start of construction to the delivery and normal use.
Fulfilling the promise with speed, Joylive Elevator handed over a satisfactory answer to Kunshan citizens!
Begin to disassemble the old elevator
December 7, begin to install
December 13, Commissioning and factory inspection
December 16, Acceptance
December 17, obtain mark
December 17, delivery